Augusta Concrete Patios A commercial patio carries more traffic in a week than a home patio sees in a year, and it has to keep trading while you pour it. Both facts change the slab before anyone picks a finish. Free on-site quote, usually within two working days.

The load is footfall and service carts rather than vehicles, so thickness matters less than jointing and base. Five inches over six of compacted stone handles seating; six inches goes where staff wheel kegs, bins or bus carts on the same line every day.
The layout drives the joints, not the building grid. Control joints have to land where the slab will crack anyway, which on a courtyard means at column lines and re-entrant corners, and ideally under furniture rather than across a walking route.
Phasing comes before mix design. Half the seating stays open, the pour is split at a construction joint, and the closed half is fenced rather than taped so nobody walks a fresh slab at closing time.
Falls are set to 2% away from the building and toward a drain that exists, not one on a drawing. Standing water on a restaurant patio is a slip claim and it will find any dip of a quarter inch.
Surface finish is chosen for wet slip resistance, not for photographs. A light broom or a fine exposed aggregate keeps grip when it rains; a smooth trowelled finish outdoors is a liability.
Sealer goes on at 28 days, and on a food-service patio it is resealed on a schedule because grease and citrus will etch an unsealed slab within one season.
Quoted per project. Area, thickness, jointing, finish and phasing all move the number, and out-of-hours work to keep the business trading is a genuine premium rather than a markup.
A courtyard poured in one lift with joints on the building grid will crack diagonally at every column within two summers. The grid has to follow the slab, not the architecture.
We cover Augusta, Columbia County and the South Carolina side of the CSRA, including and 34 more areas.
Foot traffic after about five days and furniture at seven. Heavy planters and fixed seating wait the full 28 days, because point loads on a slab that has not reached strength leave permanent marks.
Usually yes, in phases split at construction joints. It costs more and takes longer than a single pour, and for most businesses that is still cheaper than shutting the outdoor seating for a fortnight.
A light broom or fine exposed aggregate, sealed and resealed on a schedule. Both keep grip when wet and hide the wear that a smooth trowelled slab shows within a season.
Tell us what you need. We answer the same day, and the on-site visit is free.
Call (762) 320-6343 and we will come out, measure, and leave you a written quote. There is no charge for the visit and no obligation afterwards.